Modular Unit

Modular

A Building Permit is required for the installation of commercial modular facilities, including:

  • Construction trailers
  • Modular offices
  • Similar facilities

Application Process

You must apply online through San Joaquin County’s Online Permitting System. First time users will need a valid email address to set up an account. It takes about 5 minutes to create a new account.

 Apply Online

Step 1.REGISTER AS A USER

For first time users, as noted above, you will need to register for a new account with our Online Permitting System. If you have an account, please continue with Step 2 below.

To create an account, click on "Apply Online" above to be routed to the Online Permitting System login page. Click on "CREATE AN ACCOUNT" in the lower right corner, and register with your email address.

You will be asked to provide the following information to open an account.

  1. Choose a username and password
  2. Personal and Contact Information
  3. License Numbers if you are registering as a licensed professional

After you register, you'll receive a confirmation email.

Once you confirm your account, you're ready to apply.

Step 2.MAKE SURE YOU HAVE TIME TO APPLY

Building Permit applications take about 20 minutes to complete. If you are unable to complete the application you can save your progress and return at a later time, however, the application will not be reviewed until it is submitted.

Step 3.SUBMIT APPLICATION

The following items are required to submit an application: 

  1. Site plan
  2. A compete set of construction drawings, including:
    1. Foundation plans and calculations prepared by a California engineer or architect
    2. Complete floor plans
    3. Disabled access (plans and details)
    4. Details of all decks, secondary exits, stairs, steps, etc.
    5. Housing and Community Development approved use and specifications.
  3. Structures within a flood or fire hazard zone shall be designed in accordance with San Joaquin County Ordinances. For information regarding flood zones, please contact the Department of Public Works. For information regarding fire hazard zones, please contact the Fire Prevention Bureau or your local fire department.

Step 4.INTAKE AND PLAN CHECK

Building staff will review your submitted application and documents for completeness. You will be notified by email when additional information or action is required. Once your application is determined to be complete, and the appropriate fees have been paid, your application and plans will be submitted for plan review. Log into your Accela account to track the progress of your project as it advances through the plan review process. Upon approval, staff will provide you with the applicable requirements for permit issuance.

Step 5.NEXT STEPS:

  1. Staff will contact you by email to complete the intake process.
  2. When your application is accepted, you will be notified to pay fees online.
  3. Upon approval, staff will contact you for applicable permit issuance steps.